Testing and verification
The machine manufacturer or the installer of the UCC T5 is responsible for ensuring that the following testing and verification is performed to the appropriate standard:
- Verification that the electrical equipment is in compliance with the technical documentation
- Continuity testing of the protective bonding circuit
- Insulation resistance tests
- Functional tests, particularly those related to safety and safeguarding
NOTE: It is strongly recommended that any measuring equipment is regularly checked for accuracy. An initial ‘pass off' test should be performed prior to normal use.
System performance
Advisory
It is recommended that periodic metrology tests are performed in order to identify any faults in subsystems e.g. air bearings, structure, cables software etc.